Facility Construction

The University of Michigan has funded the expansion of the High Field Science laser laboratories to accommodate the ZEUS facility. The cleanroom (ISO 7) that houses the laser system and laser beam lines has been substantially extended. The building renovation added two new target areas (TA1 and TA2), a new experimental control room, new target preparation facilities and a new laser control room.

 Below are some photos of the building renovation and the ZEUS facility construction.

The old laboratories were completely removed to make space for the extended laser clean room, new ZEUS target areas experimental control room and target facilities (March 2021).
Cement was poured into the building for the thick radiation shielding walls and floor (May 2021).
The concrete shielding walls for the new Target Area 1 (right) and Target Area 2 (left) (July 2021).
The radiation shielding was extended to the full height of the building to protect the upper level offices (August 2021),
The new laser cleanroom (not yet clean!) (September 2021).
The target areas have thick, rolling shielding doors that close before laser shots (September 2021).
The new Target Area 1. The window in the shielding wall will allow a long focal length focusing geometry (September 2021).
The new corridor running alongside the experimental control room (October 2021).
The experimental control room – new furniture to come (October 2021).

 

The installation of the Amplitude Pulsar front end (November 2021).

The building renovation is completed (November 18, 2021).

 

Optical tables for the ZEUS amplifiers installed in a clean room (November 2021).

 

500 TW experimental chamber in the Target Area 2 (December 2021).

 

Two ATLAS 100 Nd:glass pump lasers designed to pump the final ZEUS amplifier installed in a clean room (December 2021).

 

Clean room with a 500 TW compressor vacuum vessel and a beam line going into the ZEUS Target Area 3 (January 2022).

 

Arrival of the ZEUS switch yard #2 vacuum vessel (April 2022).

 

ZEUS switch yard #2 vacuum vessel in the lab (April 2022).

 

Arrival of the ZEUS 3PW compressor and switchyard #1 vacuum vessels.

 

A crew from the UofM Moving and Trucking are handling switchyard #1 vacuum vessel (May 2022).

 

Moving of the switchyard #1 vacuum vessel into the Gerstaker bldg. loading dock (May 2022).

 

3PW compressor and switchyard #1 vacuum vessels in the ZEUS facility clean room (May 2022).

Cleaning of the 3 PW compressor and switchyard #1 vacuum vessels (May 2022).

Assembled and vacuum leak tested the ZEUS 3 PW compressor and switchyard #1 (June 2022).

 

The switchyard #3 vacuum vessels, which holds a long (~20 meters) focusing optics for laser wakefield experiments in the ZEUS facility clean room (June 2022).

Cleaning of the  switchyard #3 vacuum vessels (July 2022).

Optical tables enclosure installation is completed (July 2022).

A 12 inch diameter vacuum deformable mirror, controller and wavefront sensor in the ZEUS clean room (July 2022).

Alignment of the ZEUS 500 TW compressor (August 2022).

The University of Michigan and the University of California Irvine teams in the ZEUS experimental control room are preparing for the first user experiment (September 2022).